| 1. |
2023-2024 |
Diversion of 13.5165 Ha land for construction of LILO of 400 KV Bawana –Mandola T/L at Maharani Bagh of Power Grid Corporation Limited.
(1.48 ha Yudhister Setu) |
| 2. |
2023-2024 |
Creation of CA on 2.396 ha NFL w.r.t. Raising of Guide Bund Over River Yamuna by Northern Railways.
(2.39 ha Dhoolsiras)  |
| 3. |
2023-2024 |
Creation of CA on 20.57 ha NFL w.r.t. diversion of 14.15 ha forest land for construction of Aerocity to Tughlakabad MRTS corridor in favor of Delhi Metro Rail Corporation; Diversion of 5.2187 ha forest land for construction of underground station at Krishna Park and Elevated corridor between Keshopur to Mukarba Chowk for Janakpuri to RK Ashram Corridor of MRTS phase-IV; Diversion of 0.57435 ha forest land for construction of Elevated viaduct of length 12.1 kms from Maujpur to Majilis Park by Delhi Metro Rail Corporation.
(20.57 ha Dhoolsiras)  |
| 4. |
2023-2024 |
Development of Six- lane access controlled in Delhi portion of Delhi Saharanpur Highway from Akshardham NH-9 junction to Delhi/UP Border in the state of Delhi.
( 12 ha NTPC Ecopark ) |
| 5. |
2023-2024 |
Diversion of 13.5165 Ha land for construction of LILO of 400 KV Bawana –Mandola T/L at Maharani Bagh of Power Grid Corporation Limited. (Dwarf Species Plantation)
( 0.9 ha Dwarf plant) |
| 6. |
2022-2023 |
Diversion of 54.87 Ha. Deemed Forest Land for Development of Urban Extension Road-II NH-344M from Design Km 0+000 at NH-1 Intersection (Km 23+800, near Bankoli village) to Design Km 38+111 near Sector 24, Dwarka in the state of NCT Delhi.
(47.96 Ha Holambi & Sanoth) |
| 7. |
2022-2023 |
Creation of CA on 4.89 ha NFL w.r.t. Construction of 765 kV D/C Khetri-Jhatikara Transmission Line under Transmission System Associated with LTA Applications for Rajasthan Solar Energy Zone, Part-C.
( 4.89 ha Dhoolsiras)  |
| 8. |
2022-2023 |
Creation of CA on 4.89 ha NFL w.r.t. diversion of 54. 8724 ha forest land for Development of Urban Extension Road-II NH-344M from Design Km 0+000 at NH-1 Intersection (Km 23+800, near Bankoli village) to Design Km 38+111 near Sector 24, Dwarka in the state of NCT Delhi.
( 5.01 ha Dichaon Kalan ) |
| 9. |
2022-2023 |
Creation of CA on 8.11 ha NFL w.r.t. diversion of 8.11 ha forest land for Common Central Secretariat 1, 2 & 3.
(8.11 ha Dhoolsiras) |
| 10. |
2022-2023 |
Creation of CA on 4.61 ha NFL w.r.t. diversion of 4.19 ha of forest land for Delhi-Ghaziabad-Meerut RRTS Corridor.
(4.61 ha Dhoolsiras ) |
| 11. |
2021-2022 |
Diversion of 13.5165 Ha land for construction of LILO of 400 KV Bawana –Mandola T/L at Maharani Bagh of Power Grid Corporation Limited.
(12.04 ha Garhi Mandu (5.3 ha), Shastri park near yudhister setu (4.3 & 2.44 ha)) |
| 12. |
2021-2022 |
Diversion of 10.9736 Ha land for construction of LILO of 400 KV Bamnauli-Jhatikara T/L at Dwarka of Power Grid Corporation Limited.
( 10.98 ha )  |
| 13. |
2020-2021 |
Diversion of 27.68 ha land for Construction of 1) LILO of 400 KV Samaypur- Bamnaulit/Lilo of 220 KV BTPS-Mehrauli/L at Tuglakabad and Diversion of 6.944 ha land LILO of 220 kV BTPS - Mehrauli TL at Tuglakabad & 220 kV Okhla - Tuglakabad TL.
( 35.73 ha Yamuna bank metro statio)n  |
| 14. |
2020-2021 |
Construction of Dwarka Expressway of Delhi Package-1 Shiv Murti to Delhi , NHAI Project (10 ha) or Maintenance of CA land (588m) over 2 ha wrt Development of Urban Extension Road –II NH-344M from Design Km 0+00 at NH-1 intersection (Km).
( 12 ha NH-24 ) |
| 15. |
2019-2020 |
Construction of flyover and underpass between Central Mahipalpur bypass road and Airport road near Hanuman Mandir adjoining NH-8 New Delhi
( 1.81 ha NH-24) |
| 16. |
2016-2017 |
Diversion of 19.9 ha. of land at Vinod Nagar Depot, for construction of DMRC Depot.
( 19.9 ha) |
| 17. |
2015-2016 |
Diversion of 7.3849 Ha land for construction of for four DMRC Phase II Project (i.e Trilok Puri Metro Station, R.K Puram, Mayapuri Metro Station, Dhaula Kuan) and 0.97 ha Penal compensatory afforestation.
(8.354 ha) |